Royal Hallamshire Hospital 4 Theatre Upgrade Refurbishment
Client - O&P Construction
Contract Value - £1.3m
Contract Details - Mechanical
Works Duration - Jun 22–Mar 24
- Full Mechanical refurbishment of 4 operating theatres, phased over 18 months.
- 4 full theatres consisting of LTHW, Domestic Waters, AC and ventilation from plant room to theatre
- Each Theatre comprises new AHU built and fitted to HTM requirements
- Each theatre fully commissioned and validated to HTM requirements.
- New BMS system to control all aspects
- New Medical Gas Package to all theatre areas